Bill St. Clair, Saturday, 14 July, 2012

My neighbor, Wali, has been working for a long time on plans for a solar pole barn, to supply part of the power needs of the Abode of the Message, and for storage. Frank, of Jones Boys Construction, who I still think of as "Weasel", though he's been discouraging that nickname of late, has been working for the last week preparing the ground for it. He finished yesterday, and the building materials were delivered. Below are some photos. Click on any one for a higher-resolution version (most 1200x900 and 350K to 550K in size).

Construction is scheduled to begin on Monday. I'll add more photos as it progresses.

Quick jump: July 13 16 17 18 19 20 24 26 27 August 2 14 15 17 September 10 overview

Friday, 13 July, 2012

09-weasel-closeup-600x670.jpg
Frank (Weasel) of Jones Boys Construction
08-weasel-600x450.jpg
Frank (Weasel) of Jones Boys Construction
01-delivery-truck-599x380.jpg
The delivery truck
02-delivery-600x450.jpg
The forklift transporting a load
03-delivery-600x450.jpg
Another shot of that load
04-materials-600x450.jpg
Materials
05-materials-600x450.jpg
Materials
06-roof-support-600x450.jpg
The roof supports. Note the long side for the solar panels
07-roof-support-closeup-600x450.jpg
Close-up of a roof support
10-forklift-600x450.jpg
Close-up of fork-lift

Monday, 16 July, 2012

11-post-hole-600x450.jpg
Post holes
12-post-bases-600x450.jpg
Concrete bases for posts
13-wood-laid-out-600x450.jpg
Wood laid out

Tuesday, 17 July, 2012

14-poles-placed-600x450.jpg
Poles placed in holes
15-poles-secured-600x450.jpg
Poles secured
17-pole-base-600x450.jpg
Bottom of secured pole
16-two-poles-450x600.jpg
Two front secured poles

Wednesday, 18 July, 2012

Weasel spread white stone inside the posts.

Thursday, 19 July, 2012

The workers were here, but got nothing visible done.
18-post-with-white-rock-450x600.jpg
Pole with white rock

Friday, 20 July, 2012

20-front-topped-600x450.jpg
Front topped
21-side-topped-600x450.jpg
Side topped
19-front-topped-closeup-450x600.jpg
Front topped close-up

Tuesday, 24 July, 2012

21-roof-supports-north-600x450.jpg
Roof Supports from north
22-roof-supports-south-600x450.jpg
Roof supports from southwest

Thursday, 26 July, 2012

23-roof-begins-600x450.jpg
Roof paneling begin

Friday, 27 July, 2012

24-roof-continues-600x450.jpg
Roof paneling continues
25-back-roof-begins-600x450.jpg
Back roof paneling begins
26-side-view-600x450.jpg
Side view
27-inside-600x450.jpg
Inside view

Friday, 27 July, 2012

28-front-roof-complete-600x450.jpg
Front roof complete

Thursday, 2 August, 2012

29-siding-workers-600x450.jpg
Nailing siding
30-back-siding-from-front-600x450.jpg
Front view with back siding in place

Tuesday, 14 August, 2012

31-new-roof-for-old-shed-600x450.jpg
New roof for old maintenance shed
32-cut-road-for-conduit-450x600.jpg
Cut road for power conduit

Wednesday, 15 August, 2012

33-conduit-materials-600x450.jpg
Conduit materials
34-conduit-materials-closeup-600x450.jpg
Conduit materials close-up
35-conduit-ditch1-450x600.jpg
Conduit ditch 1
36-conduit-ditch2-450x600.jpg
Conduit ditch 2
37-conduit-ditch3-600x450.jpg
Conduit ditch 3
38-conduit-ditch4-600x450.jpg
Conduit ditch 4

Friday, 17 August, 2012

39-wali-on-the-tractor-600x450.jpg
Wali on the tractor

Monday, 10 September, 2012

40-solar-panels-delivered-600x450.jpg
Solar panels delivered!
41-solar-panels-delivered2-600x450.jpg
Lots of solar panels

Overview Photos

overview-01-0718am-600x450.jpg
Wednesday, July 18, 8am
overview-02-0719noon-600x450.jpg
Thursday, July 19, 1pm ("f'ing excavator")
overview-03-0721am-600x450.jpg
Saturday, July 21, 7am
overview-04-0725am-600x450.jpg
Wednesday, July 25, 8am
overview-05-0728am-600x450.jpg
Saturday, July 28, 7:15am
overview-06-0801pm-600x450.jpg
Wednesday, August 1, 1:20pm
overview-07-0803am-600x450.jpg
Friday, August 3, 6:50am
overview-08-0814pm-600x450.jpg
Friday, August 14, 6:50am
overview-09-0815am-600x450.jpg
Saturday, August 15, 8:41am
overview-10-0831pm-600x450.jpg
Friday, August 31, 1:23pm